(Solved): A project close-out is considered completed when all of the following are true EXCEPT: ATwelve mont ...



A project close-out is considered completed when all of the following are true EXCEPT: ATwelve months of continuous financial contribution is documentedBLessons learned have been documentedCKnowledge sharing is made available across the organizationDProcess owners are proficient with the new proceduresECustomer has confirmed that requirements have been met