Determine the present value of a project's ending cash flow (ECFD) using the following information: initial capital cost
-$142,000; decrease in net working capital
=$15,500; salvege value
-$27,942; CCA rate
-30%; tax rate
-35%; discount rate
-10%; project life -5 years. Round to the nearest dollar.