Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*. *Holding cost
=$(3.50)/()unit/week; setup cost
=$150; lead time
=1week; beginning inventory
=40. Develop a lot-for-lot solution (enter your responses as whole numbers).