1 00:55:49 The network diagram and task times for a project are shown below.
\table[[Task,Duration (days)],[A_(1),9],[A_(2),5],[A_(3),9],[A_(4),8],[A_(5),1]]
What is the slack for activity
A_(3)
?
days