12 In a resource-constrained project the third priority in assigning resources is usually given to activities with the Multiple Choice eBook Defremones

_(_())_(_())

smallest duration.

_(_())_(_())

least slack.

_(_())_(_())

most slack.

_(_())_(_())

lowest identification number.

_(_())_(_())

highest cost. Mc Grae MII 12 of 20