Home / Expert Answers / Operations Management / 3-work-through-the-revised-simplex-method-step-by-step-to-solve-the-following-problem-maximize-z-pa628

(Solved): 3. Work through the revised simplex method step by step to solve the following problem. Maximize Z ...



3. Work through the revised simplex method step by step to solve the
following problem.
Maximize Z = X1 + 2X2 + 4X3
S.T.
3X1

3. Work through the revised simplex method step by step to solve the following problem. Maximize Z = X1 + 2X2 + 4X3 S.T. 3X1 + X2 + 5X3 <= 10 X1 + 4X2 + X3 <= 8 2X1 +2X3<=7 X1, X2, X3 >= 0


We have an Answer from Expert

View Expert Answer

Expert Answer


Maximize z=x1+2x2+4x3 Subject to 3x1+x2+5x3 <=10 x1+4x2+x3 <=8 2x1+2x3 <=7 x1>=0, x2>=0, x3>=0 Given linear problem is a stnadard linear problem so we can add slack variables to get Equations from given inequalities. 3x1 +x2 + 5x3 + s1 = 10 x1 + 4×2
We have an Answer from Expert

Buy This Answer $5

Place Order

We Provide Services Across The Globe