Home /
Expert Answers /
Civil Engineering /
4-tablel-consider-the-project-information-in-table-1-showing-the-wbs-elements-comprising-the-ent-pa368
(Solved): 4) Tablel: Consider the project information in Table 1, showing the WBS elements comprising the ent ...
4) Tablel: Consider the project information in Table 1, showing the WBS elements comprising the entire scope of a project, planned dates in baseline schedule, and actual/planned in updated schedules. The project's planned duration was 100 days. Measurement of work element progress is by the duration method. i. Draw the baseline schedule of the project as a bar chart. ii. Draw the updated schedule for 3rd update as a bar chart; Data Date (DD)=75d (Hint: you can combine bar charts for baseline and updated schedules in one chart, if you * "A" denotes an actual date, e.g. " 11 - A" means an prefer) actual start on day 11. All other dates are planned iii. Calculate the planned project progress by time from the baseline schedule. iv. Calculate the actual project progress on the DD of 75d. v. Comment on the project time performance using: a. Project progress b. Project updated completion date vi. Analyze the reasons of delay vii. Suggest suitable managerial actions to mitigate (overcome) the delays