5. For the following schedule, draw the precedence network diagram, perform the CPM calculations, ...
5. For the following schedule, draw the precedence network diagram, perform the CPM calculations, mark the critical path, and complete the table. ES EF LS LF TF FF Activity Duration Precedent A B 3 ? 8 A (SF) D 7 A, B E 6 D (SS, 3) F 3 D F (SS, 2) G 5 F (FF) CRITICAL PATH ???