(Solved): (a) Draw a network diagram given the following information: Activity Duration Predecessor A B,C B,C ...
(a) Draw a network diagram given the following information: Activity Duration Predecessor A B,C B,C B,C C G.H D.E (b) A project has been defined for the network and their required times (days) for completion below. Calculate the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF) and slack. Show the critical path. 1 (2) B (4) D (1) G (1) A (1) ABCDEFGHI C (1) 284226000 10 10 E (2) F (2) H (1) K (4)