Home / Expert Answers / Operations Management / a-draw-a-network-diagram-given-the-following-information-activity-duration-predecessor-a-b-c-b-c-pa743

(Solved): (a) Draw a network diagram given the following information: Activity Duration Predecessor A B,C B,C ...




(a) Draw a network diagram given the following information:
Activity
Duration
Predecessor
A
B,C
B,C
B,C
C
G.H
D.E
(b) A proje
(a) Draw a network diagram given the following information: Activity Duration Predecessor A B,C B,C B,C C G.H D.E (b) A project has been defined for the network and their required times (days) for completion below. Calculate the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF) and slack. Show the critical path. 1 (2) B (4) D (1) G (1) A (1) ABCDEFGHI C (1) 284226000 10 10 E (2) F (2) H (1) K (4)


We have an Answer from Expert

View Expert Answer

Expert Answer


We have an Answer from Expert

Buy This Answer $5

Place Order

We Provide Services Across The Globe