A. Draw an Activity-on-Node (AoN) diagram for the project (5 points) B. Perform forward and backward pass calculations and list the schedule dates for all activities in tabular form which include the early start (ES), early finish (EF), late start (LS), late finish (LF) and total float (TF). (15 points) C. Identify the critical path. (5 points) \begin{tabular}{|c|c|c|} \hline Activity & Duration & Predecessor(s) \\ \hline A & 2 & - \\ \hline B & 1 & A \\ \hline C & 4 & B \\ \hline D & 3 & B \\ \hline E & 3 & B, C \\ \hline F & 3 & E \\ \hline G & 4 & D, E \\ \hline H & 2 & E, F \\ \hline I & 8 & C \\ \hline J & 5 & G, H, I \\ \hline \end{tabular}