A generating station has ake following daily load cycle: \begin{tabular}{c|c|c|c|c|c|c} Time (H ...
A generating station has ake following daily load cycle: \begin{tabular}{c|c|c|c|c|c|c} Time (Hains & 0?6 & 6?10 & 10?12 & 12?16 & 16?20 & 20?24 \\ Load (Miv) & 40 & 50 & 60 & 50 & 70 & 40 \end{tabular} Drow the load Carve and find: (1) The maximum demand (2) Units generated per day Average load: and load factor