(Solved): A housing project consists of activities as listed in the table. Compute the cement requirement base ...
A housing project consists of activities as listed in the table. Compute the cement requirement based on early start and late start times. Also prepare a graph for cumulative cement requirement. What is the minimum and maximum requirements of cement up to the 8th week:
Activity
Duration in Weeks
Total Cement Required in Tons per activity
1-2
4
20
2-3
4
24
2-4
6
18
2-5
2
10
3-6
2
20
4-6
8
24
5-6
4
20
5-7
6
30
6-7
8
40
Level the resources
Allocate the resources if there is a constraint of 10 T of cement available per week and also find the duration of the project?