  • A housing project consists of activities as listed in the table. Compute the cement requirement based on early start and late start times. Also prepare a graph for cumulative cement requirement. What is the minimum and maximum requirements of cement up to the 8th week:
ActivityDuration in WeeksTotal Cement Required in Tons per activity
1-2420
2-3424
2-4618
2-5210
3-6220
4-6824
5-6420
5-7630
6-7840

  • Level the resources
  • Allocate the resources if there is a constraint of 10 T of cement available per week and also find the duration of the project?



We have an Answer from Expert