(Solved): (a) Plot the mass diagram for the earthwork quantities contained in the accompanying table. The ini ...
(a) Plot the mass diagram for the earthwork quantities contained in the accompanying table. The initial ordinate has been arbitrarily set at \( 5,000 \mathrm{~m}^{3} \). (b) Calculate the total earthwork costs for this project using the following data. Free haul distance \( =300 \mathrm{~m} \) Excavation costs (including \( 300 \mathrm{~m} \) free haul) \( =\$ 5.00 / \mathrm{m}^{3} \) Borrow (including cost of hauling) \( =\$ 10.50 / \mathrm{m}^{3} \) Cost of overhaul \( =\$ 7.00 / \) sta-m Cost of waste is included in cost of excavation.