A.) Using the data below, calculate the Crash Cost per week for each Activity. B.) If you had to crash the project by 5 days at the minimum cost, which Activites would you crash? What would the total crash cost be? Time (Wks) Cost ($) Activity Normal Crash Normal Crash Critial Path A 4 2 4000 7000 NO B 5 3 2000 4000 YES C 2 1 1000 1500 YES D 6 4 5000 9000 NO E 3 2 3000 5000 YES F 4 2 1500 3000 YES