Answer these questions for the following simple set of project tasks. Task times are shown in hours.
a. What is the expected

Answer these questions for the following simple set of project tasks. Task times are shown in hours. a. What is the expected time that all five tasks will be completed? Answer is complete but not entirely correct.


We have an Answer from Expert

View Expert Answer

Expert Answer


Solution: From the given project network diagram, the possible paths in the network and the length of each path is as listed below: 1) A-C-D = 4 + 2 + 4 =