Calculate the cycle time of the following business process.
The cycle times of included times and the probabilities of differ???????

Calculate the cycle time of the following business process. The cycle times of included times and the probabilities of different XOR-split branches are all given. Please list the math steps of your calculation. (8 marks)


We have an Answer from Expert

View Expert Answer

Expert Answer


Observe that there are multiple 'paths' from start to finish. The first step is to identify these paths. Below are the possible paths - Path1: Start -