(Solved): Calculate the precedence diagram given below and answer the following questions: 1. The total durat ...
Calculate the precedence diagram given below and answer the following questions: 1. The total duration of the project is days 2. The total float of Activity G is days 3. The free float of Activity F is days 4. The latest finish date of Activity G is Day (Note: the number under each box represents the duration of the activity) (Unit of duration: day)