Can you help this question?
1. Consider the job list given in Table A, and assume that all jobs are available at t=0 (i.e. ignore the release times given in the table). Construct job sequences in order to minimize the following objectives. Report mean flow time, number of tardy jobs, and mean tardiness for the constructed sequences. a. Average flow time b. Number of tardy jobs C. Maximum lateness Job Due Date Processing Release Time Time 1 a 10 0 12 b 3 0 10 ? 3 9 d 10 2 14 e 4 8 f 2 5 9 8 4 6 12 h 1 10 15 3 11 15 6 18 Table A. Job List for Welding Operation i j 25