Determine the productivity rate for the work provided below based on cycle time analysis. (Round to the nearest thousandth) Type of work—hauling materials from the borrow pit Average cycle time—25 minutes Truck capacity—13 tons Crew—1 operator Productivity factor—0.83 System efficiency—33 minutes per hour