Draw an activity network diagram and compute the earliest completion time of the project using EST/ECTConsider the project with the following dependency matrix. \table[[Activity,Predecessor,Activity Time (Days)],[1,,2],[2,1,5],[3,2,7],[4,2,3],[5,2,4],[6,4,5,6],[7,3,6,3],[8,6,7,8]]