(Solved): Given is a CPM project network diagram as shown below a) The Project Completion time = Blank 1 days ...
Given is a CPM project network diagram as shown below a) The Project Completion time = Blank 1 days. b) The Earliest Start time, ES, of Activity G= Blank 2 days c) The Latest Finsh time, LF, of Activity C= Blank 3 days d) The critical activities are = Blank 4 (ex. Fill in the answer as: ABCD)