(Solved): Hollier Method #I Four machines used to produce a family of parts are to be arranged into a GT cell. ...



Hollier Method #I Four machines used to produce a family of parts are to be arranged into a GT cell. The from-to data for the parts processed by the machines are shown in the table below: \table[[,To:],[From:,1,2,3,4],[1,0,10,0,40],[2,0,0,0,0],[3,50,0,0,20],[4,0,50,0,0]] a. Determine the most logical sequence of machines for this data use Hollier Method #I.

->

b. Construct the flow diagram for the data, showing where and how many parts enter and exit the system. (Explanation: show the sequence of machines you've calculated above, then show the flow of items - from and to - using arrows between machines).



We have an Answer from Expert

View Expert Answer

Expert Answer


We have an Answer from Expert

Buy This Answer $5