(Solved):
install copy machines. Use the Learning Curve Excel template to answer the following questions: a. ...
install copy machines. Use the Learning Curve Excel template to answer the following questions: a. If the time required to install the first copy machine is estimated to be five hours, what is an estimate of the time rew technician to install the third and fourth copiers? Round your answers to one decimal place. For \( x=3 \) it takes For \( x=4 \) it takes b. If the learning rate changes to 55 or 90 percent, what is an estimate of the time required by a new technician to install the third and fourth copiers? Round your answers to one decimal place. For \( x=3 \) and a \( 55 \% \) LC, it takes For \( x=4 \) and a \( 55 \% \) LC, it takes For \( x=3 \) and a \( 90 \% \) LC, it takes hours For \( x=4 \) and a \( 90 \% L C \), it takes hours