on 1 After three months on the job (July 1"), the contractor concluded that 26% of Excavation was completed (Site work, Fencing, and Paving are 100% completed), 80% of Electrical was completed, and 40% of Plumbing was completed. The project has cost the contractor a total of $110, 250 as of July Ist. Using earned value concepts, analyse the project performance and briefly explain the performance to the client 1201 Activity April May July August Sept Site work Cost June $23,000 Fencing $5,000 Paving $20,000 Excavation $30,000 EVU Foundation $50,000 Slabs, Column $45,000 and Beams Electrical $6,000 Plumbing $15, 500 $18,000 Exterior and Interior walls Roof $8,000 $30,000 Interior Finishes