The network diagram of a project is shown below.
What is the critical pass?
A-B-D-E-G A-C-D-E-G A-B-D-F-G A-C-D-F-GPLEASE ANSWER THE FOLLOWING 4 QUESTIONSWhich activities have slack time?
\[
A, B, C \quad B, F \quad B, C, D, E \quad A, C
\]
QUESTION 4
Which activity has the high

The network diagram of a project is shown below. What is the critical pass? A-B-D-E-G A-C-D-E-G A-B-D-F-G A-C-D-F-G Which activities have slack time? QUESTION 4 Which activity has the highest slack time and what is its slack time?