PLEASE ANSWER THE FOLLOWING 4 QUESTIONS
The network diagram of a project is shown below. What is the critical pass? A-B-D-E-G A-C-D-E-G A-B-D-F-G A-C-D-F-G
Which activities have slack time? A,B,CB,FB,C,D,EA,C QUESTION 4 Which activity has the highest slack time and what is its slack time? A - 7 B ?1F?2E?6