Home / Expert Answers / Operations Management / question-3-20-marks-given-the-following-information-related-to-the-main-activities-of-your-project-pa415

(Solved): Question 3 (20 Marks) Given the following information related to the main activities of your project ...



Question 3 (20 Marks) Given the following information related to the main activities of your project. Activity Predecessor Duration in days A 4 B 6 C A 3 D B 5 E C 6 F D 4 3.1 Draw the network diagram for the project (5 marks) 3.2 Using the forward and backward pass method, determine the slack for each activity. Input your information on the table provided (13 marks) Activity Duration ES EF LS LF Slack A 4 B 6 C 3 D 5 E 6 F 4 3.3 Determine the critical path and the duration of the project using the forward and backward pass method. (2 marks



We have an Answer from Expert

View Expert Answer

Expert Answer


We have an Answer from Expert

Buy This Answer $5

Place Order

We Provide Services Across The Globe