\table[[Activity,Predecessor,\table[[Activity],[Time]]],[A,-,3],[B,-,5],[C,-,9],[D,A,B,6],[E,B,6],[F,C,5],[G,E,F,7],[H,D,11]] Given the project data above, draw the 2-cell project network and answer the following questions: What activities are on the critical path of the project? What is the project duration?