The team members of Argo consultants have developed the following schedule of activities for their upcoming project, using their best estimate of completion times.
Draw the project network.
Can they complete the project in 70 days? What is the project completion time?
Show Forward pass and Backward pass. Give the Critical Path.
You can use the space below or upload the network.
Activity
Time (days)
Immediate Predecessor
A. Find Location
8
---
B. Write Venue
4
A
C. Obtain approval from the professor
6
B
D. Complete event planning
21
C
E. Do industry background research
17
---
F. Write the final paper
12
D, E
G. Write an oral report
10
D, E