Use the decreasing time list algorithm to schedule these tasks on two machines: 9 minutes, 6 minutes, 3 minutes, 4 minutes, 8 minutes. How much time does the resulting schedule require?
1. Use the decreasing-time-list algorithm to schedule these tasks on two machines: 9 minutes, 6 minutes, 3 minutes, 4 minutes, 8 minutes. How much time does the resulting schedule require? O 17 minutes O 16 minutes O 15 minutes O 14 minutes