(Solved): When completing a MRP schedule you are given the following information. Cafetv stock 0 . lead time ...
When completing a MRP schedule you are given the following information. Cafetv stock 0 . lead time 2 weeks, EOQ 50 a) If the projected avanaunce for period 1 is 35 units. What would be the projected available balance for period 4 ?
To calculate the projected available balance for period 4, we need to first calculate the net requirements for each period between period 1 and period 4. Given that the initial stock is 0 and the economic order quantity (EOQ) is 50, we can calculate the reorder point as follows:Reorder Point = Lead time demand + Safety stockLead time demand = Projected demand during lead time = 35 unitsSafety stock = 0 (given)Reorder Point = 35 + 0 = 35 unitsThis means that we should place an order for 50 units when the projected available balance reaches 35 units. The order will arrive after a lead time of 2 weeks, which means that we need to have enough stock to cover the demand during that lead time.Using this information, we can calculate the net requirements for each period:- Period 1: Projected demand = 35 units. Net requirements = 35 - 0 = 35 units.- Period 2: Projected demand = unknown. Net requirements = 50 (EOQ) - 35 (projected available balance at end of period 1) = 15 units.- Period 3: Projected demand = unknown. Net requirements = 15 (reorder point) - 0 (projected available balance at end of period 2) = 15 units.- Period 4: Projected demand = unknown. Net requirements = 50 (EOQ) - 15 (projected available balance at end of period 3) = 35 units.