(Solved): You 6- Using Meyerhof method for point load determine Qui D = 0.5m, closed ended pipe pile SAND $=3 ...
You 6- Using Meyerhof method for point load determine Qui D = 0.5m, closed ended pipe pile SAND $=30° Y=18KN/m³ 8m 12m. SAND d=34° Y = 19 kN/m³ SAT FOS=2,5 K=1.5K. 8 = 0.654